Please note that there will be construction at Town & Country Village starting September 23rd and is expected to be completed by October 16th. This is a provisional work schedule and may be subject to change.
Asphalt Repair – Wednesday, September 23rd
Several trucks and some disruption, but no restrictions to shops, restaurants, etc.
Pavers, Embarcadero Entrance Area – September 28th – October 7th
Entrance/exit open, but traffic control will be in place, resulting in tighter flow.
Pavers, Area #5 – Monday, October 12th – Friday, October 16th
Pavers, Area #7 – Monday, October 12th – Friday, October 16th
Sealcoat and Re-Stripe
Thank you for your patience during construction. We apologize for any delays or inconvenience this may cause, and we’re committed to keeping the center beautiful and improving your shopping and dining experience.